Surface Water Management Plan


As of August, 2018 this project is still in progress with a final completion date slated for summer 2019. Due to high water saturation, the ground conditions on this project require extensive de-watering. The de-watering is imperative since the overall goal of the project is to implement a Surface Water Management Plan (SWMP). This particular SWMP requires a large engineered pond (with liner) and ditch system. This system incorporates and inlet/outlet to the pond. It’s overall purpose is to capture all water runoff from the gas plant into the pond. When completed there will be an additional 3.5 Meters of fill to ensure greater ground stability. Engineering measures are being worked out to lower the current water table by over 3 Meters. This will ensure greater ground stability for the construction phase.

Implementation of GEOWEB®


Team Resources managed the installation of GEOWEB® on this pad. This product uses a network of 3D interconnected cells. When used to specifications infill is confined, resistant to movement and stable. The GEOWEB® system confines infill material. Thus it ‘transforms’ cohesion-less soil type infill into strong and stable material. GEOWEB® can be used for a host of applications such as roadways and steep embankments. Team Resources added, in conjunction with the GEOWEB®, 4-6” of gravel extra above the web for extra support and stability.

Lease Construction/Clean Ups; Vulcan and Big Valley Alberta


1 Building lease and access in Vulcan Alberta.
2 Lease in Vulcan Rig Ready with conductor (Rat and mouse hole lined).
3 Lease in Vulcan Rig Ready with drill pad finished.
4 Building Production pad in Vulcan, Alberta.
5 Production Pad in Vulcan construction in progress (D6T six way).
6 Production pad in Vulcan.
7 Production pad in Vulcan (two).
8 Building drilling pad & access, Big Valley, Alberta (rough ground/terrain).
9 Laying filter clothe in wet area before padding (AB Environment mitigation conditions).

Winter Programs; Fort Mcmurrauy, Athabasca and Kearl Lake Alberta


1 Mulching in progress in Fort Mcmurrauy Fire Project
2 Fire Project New access (freeze in with snow cat then water truck).
3 Winter lease rig ready in Fire Project.
4 Winter access Rig ready in Fort Mcmurrauy.
5 Kearl lake Esso logging.
6 Processor logging on Kearl Lake winter drilling program.
7 Pile Load program – to construct plant site for Kearl Lake Esso.
8 Fire Project Freezing in the Athabasca (Engineered/Certified Load Capacity of 120,000.00lbs).
9 Fire Project Freezing in the Athabasca.

Road Construction Project LSD# 15-20-36-23W4M


Team Resources provided excellent project management for this early winter road construction project. Respecting the impending obstacle of frozen soils, Team Resources elected to stay ahead of the frost by building the road in 200 metre sections. The landowner's property was taken into consideration during early construction phase by stripping all of the top soil and sub soil to one side. This wise decision enhanced the over all project in several ways. It placed the road tight to the quarter section line putting less crop land out of production. With only one ditch cut an entire extra metre of work space was gained from only stripping one side. Once each 200 metre section of road top was complete to grade the soils were spread back into the ditch and the next 200 metre section was started.

Reclamation


1 Pump water off access then let dry step one
2 Pump water off lease and let dry
3 Topsoil spread after landscaping on lease at even distribution
4 Roto Spik topsoil to minimize compaction in soil to gain better growth
5 Roto Spik Lease
6 Access DSA was completed by Trace Environment and passed with Landowner being very satisfied

Production Pad Clean Up


1 Pull in clay material to contour and build pad
2 Facility’s set up pad completed
3 Landscape clay and prep to spread soils shooting with laser level
4 Landscape and contour clay to prep to spread subsoil and topsoil
5 Soils spread with positive drainage established
6 Soils all spread with seeding to follow Delburne mix
7 Construct clay berm as per mitigation plan and to appease Alberta Environment
8 Access Put back with seeding to follow

Battery Expansion 8-3-37-22W4M Mikwan


1 Pad before expansion
2 Pad before expansion
3 Remove and transfer soils to make workspace for pad expansion
4 North expansion
5 Tank farm area ready for facility set up
6 Final grading and with compaction complete
7 Pad dirt works completed will contouring and landscape soils at later date after pipeline and facility constructions complete